What Must Be in Place Before Work Starts on Site?

The CDM 2015 checks before work starts on site: the construction phase plan, welfare, induction, site security and what each trade needs first.

6 min read

Nicola Dobbie, Founder and CEO of The Site Book
Nicola Dobbie·Founder and CEO, The Site BookLast updated 27 November 2026

TL;DR

The CDM 2015 checks before work starts on site: the construction phase plan, welfare, induction, site security and what each trade needs first.

Listen to the audio summary

3 min · AI narration — the article below stays the full, up-to-date source. Also available on the podcast page.

Transcript

Open: This is Site Safety in Five, from The Site Book. One question from site, answered in about five minutes. Today: is your site actually ready to open, and which trades can start on day one?

Story: Start with a site in Telford, in the West Midlands. Inspectors turned up. They found no clean hot or cold water. The rest facilities weren't suitable either. The firm pleaded guilty to breaching the welfare duty under CDM twenty fifteen. HSE reported, in April twenty twenty-six, a fine of fifteen thousand, eight hundred and fifty-eight pounds, plus costs. And this wasn't the first time. HSE said the firm had breached the same law on three earlier occasions. We're starting there because welfare isn't something you add once the site gets busy. Washing water and a rest area have to be there from the first day. A pre-start check is how you show they were.

Answer: So which trades can start? None, until the basics are in place. Regulation thirteen says the site has to have welfare that meets the standard, an induction ready to give, and steps taken to stop unauthorised people getting on. That's on whoever runs the site. That welfare standard is set out in the regulations: toilets, washing, drinking water, rest, and changing and lockers where needed. HSE's guidance for principal contractors says welfare should be there from the start. And regulation twelve says the construction phase plan is drawn up before you set the site up. Not after.

Order: So work through it in order, before the gate opens. First, check the client has done its part. Arrangements made, pre-construction information passed on, and HSE notified if the job is notifiable. Next, the plan. There has to be a construction phase plan, written before setup, and it has to fit the job. Then welfare, security and induction. Toilets, washing, water and rest in place. Fencing and gates up. The induction ready to give. Finally, each trade. Competent people, briefed and ready to follow the plan.

Doing it properly: Do the plan properly. It should match the size and risk of the job. A two-week extension needs a short plan. A six-month build needs more. What matters is that it exists, it fits the job, and people have actually read it. And a plan is needed on every job, not just notifiable ones. With one contractor, that contractor writes it. With more than one, whoever runs the site does.

If you run the site: If you run the site, you turn the plan into a working site. You secure it, you provide welfare, and you make sure everyone's inducted. But each trade still carries its own duties. Before you let a trade start, take reasonable steps to check it has the skills, knowledge and experience for the role. Ask each trade to send competent people and brief its own workers, including emergency procedures. Our suggestion, not a CDM rule: ask each trade for its RAMS, reviewed and accepted before its people arrive. Then go and look, rather than taking it on trust.

Close: So that's the order. Check the client's part. Get the plan, welfare, security and induction in. Then check each trade is competent and briefed. This covers Great Britain, and it's general guidance, not legal advice. The full article, with a pre-start checklist you can copy, is on our website, The Site Book dot co dot U K. This has been Site Safety in Five.

Watch the short video

When is a project notifiable to HSE?

39 sec · AI narration with captions on screen. The article below has the full guidance.

Transcript

Not sure if your job needs an F10 to HSE?

Getting this wrong before you open the gate is a real risk.

Under CDM 2015, a project is notifiable in two ways.

First, if the work will last longer than 30 working days and have more than 20 workers at once.

Both parts must be true for that one to apply.

Second, it is also notifiable if it will exceed 500 person days.

The client must notify as soon as practicable before the construction phase begins.

And the notice must be displayed in the site office.

Check the thresholds before day one, not after.

Before work starts on site, the law expects a construction phase plan, welfare facilities, a site induction and steps to keep unauthorised people out. Each trade also needs competent people and the information to work safely.

This post covers one decision: whether your site is ready to open and which trades may start on day one. For the full process, see our principal contractor duties guide. It covers Great Britain under CDM 2015. Northern Ireland has its own CDM regulations from 2016.

What happens when the basics are missing?

In April 2026, HSE reported that a West Midlands construction company was fined £15,858 and ordered to pay £3,858 in costs. Inspectors at its Telford site found no clean hot or cold water. The rest facilities were also not suitable.

The firm pleaded guilty to breaching regulation 13(4)(c) of CDM 2015. That is the principal contractor's duty to provide Schedule 2 facilities throughout the construction phase. HSE said the firm had breached the same law on three earlier occasions.

Our view: proper washing water and a rest area are not extras to add once the site is busy. A pre-start check is how you show they were there from the first day.

What must the client have done before work starts on site?

The client sets the project up. Before you open the gate, check that the client has:

  • made suitable arrangements for managing the project, including time and resources (law, reg 4(1));

  • arranged for the facilities required by Schedule 2 to be provided (law, reg 4(2)(b));

  • provided pre-construction information to every designer and contractor (law, reg 4(4));

  • made sure a construction phase plan is drawn up before the construction phase begins (law, reg 4(5)(a));

  • notified HSE on an F10, if the project is notifiable (law, reg 6).

A project is notifiable if the work is scheduled to last longer than 30 working days and have more than 20 workers at once. Both must be true. It is also notifiable if it will exceed 500 person days. The client must notify as soon as practicable before the construction phase begins. The notice must be displayed in the site office.

What must the principal contractor have in place?

The principal contractor turns the plan into a working site. On day one you should have:

  • a construction phase plan, drawn up before setting up the site (law, reg 12(1));

  • a suitable site induction ready to give (law, reg 13(4)(a));

  • the necessary steps taken to stop unauthorised people getting onto the site (law, reg 13(4)(b));

  • facilities that meet Schedule 2, provided throughout the construction phase (law, reg 13(4)(c)).

HSE guidance for principal contractors says suitable welfare facilities should be provided from the start. Schedule 2 sets the standard: toilets, washing facilities, drinking water, rest facilities, and changing rooms and lockers where needed. Our site welfare guide covers each one. The free site welfare calculator gives the minimum toilets and washbasins for your peak headcount.

What must each trade have before it starts?

Every contractor carries its own duties, even with a principal contractor in charge. Before a trade starts, it must:

  • be satisfied that the client is aware of the client's duties (law, reg 15(1));

  • only put people on site who have, or are gaining, the necessary skills, knowledge, training and experience (law, reg 15(7));

  • give its workers supervision, instructions and information, including emergency procedures (law, reg 15(8) and (9));

  • not begin work until reasonable steps have been taken to prevent unauthorised access (law, reg 15(10)).

Whoever appoints a contractor must also take reasonable steps to check it has the skills, knowledge and experience for the role (law, reg 8(3)).

In practice, most principal contractors also want each trade's RAMS reviewed and accepted before it starts. Our guide on how to review subcontractor RAMS before work starts sets out a checklist for that.

Is a construction phase plan needed on every job?

Yes. CDM 2015 asks for a plan on every project, not only notifiable ones. With one contractor, that contractor draws it up as soon as practicable before setting up the site (law, reg 15(5)). With more than one, the principal contractor does it (law, reg 12(1)).

Our view: the plan should match the size and risk of the job. A two-week extension needs a short plan. A six-month build needs more. What matters is that it exists, it fits the job, and people have read it.

What the law says

These are the duties that apply before the first trade starts, from the Construction (Design and Management) Regulations 2015:

  • Regulation 4: client arrangements, Schedule 2 facilities, pre-construction information and the construction phase plan.

  • Regulation 6: notification thresholds and timing.

  • Regulation 8: competence of those appointed.

  • Regulation 11: the principal designer helps the client provide pre-construction information.

  • Regulation 12: the principal contractor's construction phase plan.

  • Regulation 13: induction, site security and welfare.

  • Regulation 15: contractor duties, including the single-contractor plan.

  • Schedule 2: minimum welfare facilities.

Who does what between the site and the trades?

The split depends on your role on this job.

  • Client: sets up the project, provides pre-construction information, notifies HSE if needed and makes sure a plan exists.

  • Principal contractor: draws up the plan, secures the site, provides welfare and makes sure everyone is inducted. It also coordinates the trades.

  • Each contractor: checks the client knows its duties, sends competent people, briefs its own workers and follows the plan.

If another firm is principal contractor, you still carry your contractor duties. Ask for the relevant parts of their plan and their induction before your people arrive. If your firm is the only contractor, the plan falls to you.

Our view: do not let a trade start because the principal contractor "has it covered". Regulation 15(10) puts the site security check on each contractor too. Our guide to managing subcontractors covers the stages from selection to close-out.

How to record it

Keep one pre-start checklist per job, signed and dated. In practice, it should show:

  1. The construction phase plan, with its date and who wrote it.

  2. The F10 reference and where the notice is displayed, if notifiable.

  3. Pre-construction information received, and from whom.

  4. Welfare in place: toilets, washing, drinking water, changing and rest areas.

  5. Site security: fencing, gates, signs and who locks up.

  6. The site induction content, and a record of who has had it.

  7. Emergency arrangements, first aid cover and the nearest hospital.

  8. Underground services located and marked before any digging.

  9. Each trade's RAMS reviewed and accepted, with the date.

  10. Insurance and training cards checked for each trade.

Items 7 to 10 are common practice rather than the wording of CDM 2015. In our experience, clients and insurers often ask to see them.

If you run several jobs with office support and people on site, Business is built for that. The page describes site files in one place, an attendance and live sign-in register, and an approval step before documents are issued. For the plan itself, our construction phase plan page drafts a CPP for your competent review. Nothing goes into the document without your approval.

The bottom line

Do not open a site on trust. Check that the client has done its part. Check that the plan, welfare, induction and security are in place. Then check that each trade is competent and briefed. Record it once, sign it and keep it on file.

This article is general guidance, not legal advice or a guarantee of compliance.

Sources

Create the first job pack free

Start with one real job: RAMS, CPP, site induction and sign-off evidence. No card required. Review everything before you use it.

Create my free job pack →

More articles

Why Your RAMS Keep Getting Rejected (And How to Fix Them Before Work Starts)

Five examples of gaps that can delay a RAMS review, from vague task descriptions to missing site-specific controls, and how to address them before work starts.

What should be covered in a site induction: a checklist for small firms

What a site induction should cover: the project and who runs it, site rules, hazards and controls, emergency, first-aid and welfare arrangements, reporting and ongoing briefings, plus what visitors need.

How to Generate RAMS, COSHH Assessments, and Toolbox Talks for UK Construction

Learn how to create RAMS, COSHH assessments, and toolbox talks for UK construction sites, plus how The Site Book speeds up the whole workflow.