How long is a site induction valid, and how long do you keep the records?
Is a site induction valid on another site or after a break, and how long should you keep the signed records? What CDM 2015, HSE and UK GDPR say.
7 min read

TL;DR
Is a site induction valid on another site or after a break, and how long should you keep the signed records? What CDM 2015, HSE and UK GDPR say.

A site induction has no legal expiry date, but it is only valid for the site and the risks it covered. No regulation sets how long to keep the signed records, so set a period and stick to it.
This post covers one decision: whether an induction a worker already has still counts, and how long to keep the proof. For the full process, see our guide to running a site induction.
Is a site induction valid on another site?
No. CDM 2015 asks the principal contractor to make sure "a suitable site induction is provided". HSE guidance says the induction "should be site specific and highlight any particular risks". An induction on site A covers site A. It does not cover the access route, first aid point or crane on site B.
Induct every worker on each new site, even if they were on your other job last week.
Do not accept another firm's induction, or a training card, in place of your own site briefing.
Keep it short for returning faces. Company-wide parts can be brief, but the site-specific parts cannot be skipped.
Induct visitors too. HSE says their induction should be proportionate to the visit, and escorted visitors need less detail.
When should you repeat a site induction on the same site?
The law sets no fixed interval. But the induction has to stay suitable, and training must keep up with changing risks. Under the Management Regulations, an employer must train staff when they face new or increased risks. That training must be "repeated periodically where appropriate".
HSE's CDM guidance adds that further training may be needed when tasks change, new equipment arrives or the system of work changes. Our view: re-brief or re-induct when any of these happen.
The construction phase plan is revised for a new phase, such as moving from groundworks to working at height.
New significant risks arrive, such as a crane, a demolition stage or an occupied area.
Site rules, traffic routes, welfare, first aid or emergency arrangements change.
A worker comes back after a long break and the site has moved on.
A worker's job changes, or they start using new equipment.
An incident or near miss shows the briefing did not land.
A toolbox talk can cover a small change. A new layout or emergency route usually needs a fresh, signed briefing. That is practice, not a legal rule.
How long should you keep site induction records?
We found no regulation that sets a retention period for induction records. HSE's CDM guidance does not set one either. Two other laws shape a sensible period instead.
Injury claims. In England and Wales, a personal injury claim usually has three years. The clock runs from the injury, or from the date of knowledge if that is later.
Data protection. Induction records hold personal data. UK GDPR says personal data must be kept "for no longer than is necessary" for its purpose.
Your own policy. The ICO says the UK GDPR "does not set specific time limits". It expects you to set and document your own retention periods.
Our view: keep induction records for the life of the project, plus at least three years. The ICO says you should consider whether you need to keep information to defend a possible future claim. Keep them longer only for a reason you can state, such as a reported injury. Write the period into a retention schedule, then delete or anonymise the records when it ends.
Do induction records go in the health and safety file?
Not as a rule. HSE describes the file as information needed for future work on the building, such as maintenance or demolition. It says the file should not include the construction phase plan, contractual documents or method statements. Induction records are not on HSE's list of contents to consider. Keep them with your own project records.
Who inducts whom, and who keeps the record?
When more than one contractor works on a project, CDM 2015 requires the client to appoint a principal contractor in writing. The split below follows CDM 2015. The record-keeping points are our view of good practice.
Principal contractor. Makes sure every worker on site gets the site induction, including subcontractor operatives.
Subcontractor. Must provide a site induction only where the principal contractor has not. On a single-contractor job, that falls to the contractor.
Subcontractor, always. Still owes its own people supervision, instructions and information. That includes the briefing on its RAMS.
Who keeps what. The principal contractor keeps the site induction register, and files a copy of each subcontractors RAMS alongside the Construction Phase Plan. Each subcontractor keeps its own training and RAMS briefing records.
End of the job. The principal contractor keeps its register under its own retention schedule. Ask subcontractors for copies of their briefing records before they leave site.
Agree this at the pre-start meeting, so neither side assumes the other holds the proof. Our guide to managing subcontractors has a record sheet that includes the induction date.
What the law says
CDM 2015 regulation 13(4)(a): the principal contractor must ensure that "a suitable site induction is provided".
CDM 2015 regulation 15(8): a contractor must give each worker under their control "appropriate supervision, instructions and information".
Regulation 15(9)(a): that information must include "a suitable site induction, where not already provided by the principal contractor".
Management of Health and Safety at Work Regulations 1999, regulation 13(2) and (3): training on recruitment and on exposure to new or increased risks. It must be repeated periodically where appropriate, and take place during working hours.
Limitation Act 1980, section 11(4): three years from the injury, or from the date of knowledge if later. This section extends to England and Wales.
UK GDPR Article 5(1)(e): storage limitation. Article 5(2) says you must be able to show you comply.
No regulation gives a site induction an expiry date. The CDM 2015 and Management Regulations duties apply in Great Britain. Northern Ireland has its own Construction (Design and Management) Regulations (Northern Ireland) 2016.
How to record it
Record the worker's name, employer, trade, the site and the date.
Note who gave the induction, and any language or reading support used.
Get the worker's signature, or a digital confirmation, on the day.
Give each induction a version number. When the plan changes, issue a new version and log who has had it.
Check the sign-in register against the induction list, so nobody works on site without one.
Set a retention period in your schedule and diarise the date to review or delete.
If you need a starting point, our free site induction template has blank PDF and Word versions.
If the same crews move between your jobs, see The Site Book's Business plan. Workers, subcontractors and visitors can check in and out, giving you a live view and an attendance history for site records. Site files sit where assigned site users can see the latest version. Site Supervisor logins are limited to assigned sites. Blocking check-in until a worker has completed the induction is part of Site Control, the tier above Business.
The bottom line
Treat a site induction as valid for one site and one set of risks. Induct again on every new site, and re-brief when the plan, the risks or the worker's job changes. Keep signed records for the life of the project plus a set period, and write that period down.
This article is general guidance, not legal advice or a guarantee of compliance.
Sources
CDM 2015, regulation 13: Duties of a principal contractor in relation to health and safety
Management of Health and Safety at Work Regulations 1999, regulation 13: Capabilities and training
Limitation Act 1980, section 11: Special time limit for actions in respect of personal injuries
UK GDPR, Article 5: Principles relating to processing of personal data
The Construction (Design and Management) Regulations (Northern Ireland) 2016
Create the first job pack free
Start with one real job: RAMS, CPP, site induction and sign-off evidence. No card required. Review everything before you use it.
Create my free job pack →