Building control in England
Building Control for Extensions in England
Plan building control for an extension in England: application routes, design evidence, site inspections and completion records.

TL;DR
In England, most domestic extensions need Building Regulations approval, even under permitted development. Local authority Full Plans gives a decision; Building Notice is only for eligible work and gives no advance approval. A private registered approver gives the council an initial notice. Confirm the route, notices and inspections before starting. RAMS and CPP cover separate safety duties.
Building control wants specifics — write RAMS with the job's details
Set up a free account and generate the RAMS, construction phase plan and site induction for one real job. No card needed.
Start free →In this guide
Check the approval route
Building regulations approval and planning permission are separate processes, and GOV.UK states it plainly: “Building regulations approval is different from planning permission. You might need both.” A design that qualifies as permitted development for planning purposes has only answered the planning question; it says nothing about building regulations, which is a separate legal requirement about how the work is built rather than whether you’re allowed to build it. This guide covers England only; Wales, Scotland and Northern Ireland run separate building regulations regimes.
Most ordinary extension work does not qualify for any exemption, and floor area alone doesn’t settle the question. Schedule 2 to the Building Regulations 2010 exempts, under Class 7, ground-level additions such as “a conservatory, porch, covered yard or covered way” or “a carport open on at least two sides” only where the floor area of that extension does not exceed 30m² — and, for a conservatory or porch that is wholly or partly glazed, only if “the glazing satisfies the requirements of Part K4, K5.1, K5.2, K5.3, and K5.4” of Schedule 1. Under Class 6, a detached single-storey building with no sleeping accommodation is exempt where its floor area does not exceed 30m² and it either stands at least one metre from the boundary or is built substantially of non-combustible material; a detached building with no sleeping accommodation is exempt regardless of that condition where its floor area does not exceed 15m². A standard rear extension, a loft conversion, a garage conversion, or anything over one storey falls outside these classes and needs approval in the normal way.
A Schedule 2 exemption is not unconditional even where it applies. Regulation 9(3) applies Part P (electrical safety) to a small detached building or extension that “receives its electricity from a source shared with or located inside a dwelling” — so a garden room wired from the house consumer unit still has to meet Part P, even though the structure itself is exempt. Regulation 9(2) does the equivalent for water: the Part G water-safety requirements apply where an otherwise-exempt building or extension “receives a cold or hot water supply from a source shared with or located inside” a building that is not itself Schedule 2-exempt. Check the electrical and plumbing arrangement with your building control body before treating an outbuilding or extension as entirely outside the Regulations.
Where approval is needed, there are two separate decisions to make. The first is who acts as your “relevant authority”: GOV.UK confirms “you can either choose your local authority’s building control department or a private registered building control approver.” A registered building control approver takes on the role by serving an initial notice. For sole-trader and small-firm extensions, the Building Safety Regulator’s higher-risk regime will not apply: GOV.UK describes higher-risk buildings as “at least 7 storeys or 18 metres high” and containing “2 residential units”, “a hospital” or “a care home” — well beyond a single-dwelling extension.
For an ordinary local-authority application, the second decision is how you apply: regulation 12 requires anyone carrying out building work to give the relevant authority either “a building notice in accordance with regulation 13” or “an application for building control approval with full plans ... in accordance with regulation 14” — Full Plans or Building Notice, in everyday terms. Full Plans is assessed before you build: GOV.UK states “you can expect a decision within 5 weeks, or 2 months with your consent,” so it suits work you want checked and confirmed before it starts. A Building Notice suits smaller, more straightforward jobs where you’re comfortable starting sooner: GOV.UK states “you can start work 2 days after your notice has been submitted to your BCB,” but nothing has been checked against drawings first, so compliance gets confirmed later, through inspection, rather than agreed up front.
Prepare the design evidence
Building control’s job is to check the work against whichever Parts of Schedule 1 to the Building Regulations 2010 apply to it — a schedule of requirements grouped under headings that include Part A “Structure”, Part B “Fire safety”, Part F “Ventilation”, Part G “Sanitation, hot water safety and water efficiency”, Part H “Drainage and waste disposal”, Part L “Conservation of fuel and power” and Part P “Electrical safety”, among others. Which Parts actually apply depends on the specific job: a rear extension with a new bathroom engages structure, drainage, energy and water; one that ties new wiring into a shared circuit engages Part P too, under the regulation 9(3) carve-back covered above. Ask your building control body which Parts apply to your proposal rather than assuming a standard set.
The evidence that demonstrates compliance follows from those Parts rather than from a generic checklist: drawings showing the proposed structure and how it relates to the existing building, structural calculations wherever the design depends on them — a new opening, a beam, altered foundations — drainage layouts, and, where relevant, information covering energy performance, electrical work and water systems. What counts as sufficient evidence for your specific design is a matter for the building control body reviewing it, not a fixed list any guide can supply in advance; ask what’s needed before you commission drawings, not after.
If you apply with Full Plans, regulation 14 requires a written application, signed by the applicant, describing the existing building and the proposed work, together with “two copies of the full plans, or where Part B of Schedule 1 (fire safety) imposes a requirement in relation to proposed building work, four copies of the full plans.” Regulation 14A then requires the authority to grant the application unless it “does not comply with the requirements of regulation 14” or “is not sufficiently detailed”, within the same 5-week (or 2-month, with consent) decision period GOV.UK gives applicants.
A Building Notice, given under regulation 13, skips that up-front plans review. Nothing about your design has been formally checked before you start, which is the trade-off for the faster start GOV.UK describes — “you can start work 2 days after your notice has been submitted to your BCB” — compliance still has to be demonstrated, but it happens through inspection on site rather than through a decision on drawings beforehand. Neither route changes what has to be built; only Full Plans checks it in advance, while Building Notice checks it as the work happens.
Questions for your building-control provider
Before programming the work, get written answers from your building-control provider on the application route, design evidence, required notices, inspection hold-points, change process and completion document. Keep the answers with the drawing list and inspection programme; re-confirm them if the provider or route changes.
Keep RAMS and building control distinct
Building control’s remit is compliance with the Building Regulations 2010; nothing in that legislation gives a building control body a role in approving or rejecting RAMS (risk assessments and method statements) or a construction phase plan. Those documents sit under a different regime, the Construction (Design and Management) Regulations 2015 (CDM 2015), which governs how work is planned and carried out safely rather than how the finished building performs. A client or principal contractor may ask to see your RAMS as part of their own CDM duties, and a building control body may separately ask questions relevant to its own assessment — but neither is a building-control decision on the documents themselves, and there is no general “RAMS approval” step.
The construction phase plan duty applies whether or not the job is notifiable, and it falls on different people depending on how many contractors are involved: under regulation 12(1) of CDM 2015, the principal contractor “must draw up a construction phase plan, or make arrangements for a construction phase plan to be drawn up” where the project has more than one contractor and a principal contractor has therefore been appointed, while under regulation 15(5), where you are the only contractor on the project, that same duty falls on you, to be carried out “as soon as is practicable prior to setting up a construction site.” Building control does not check that this document exists and does not assess its content; responsibility for it, and any enforcement of it, sits with the CDM regime rather than the Building Regulations 2010.
If someone raises RAMS in a building-control conversation, find out what they actually need and why, rather than assuming it’s a formal building-control requirement. A site manager, a client or a building control officer asking about site safety is not the same as a building-control decision on your design, and a RAMS review is not a route for disputing or appealing one. Keep the two conversations — compliance with the Building Regulations, and the CDM safety paperwork — separate in your own records as well as in how you respond to questions, so a query raised about one doesn’t get logged as a finding about the other.
Building Regulations roles are separate too
England's Building Regulations give clients, designers and contractors their own roles and competence duties, including principal designer and principal contractor roles. These are separate from the corresponding CDM 2015 construction-safety roles; the same organisation may perform both if competent, but a CDM appointment alone does not make a Building Regulations appointment. For a business client, where more than one contractor is expected, the client must appoint the Building Regulations principal designer and principal contractor in writing, or certify in writing that the CDM appointees also hold those roles. On a domestic extension, some client management and competence duties pass to the sole contractor or, with multiple contractors, the principal contractor unless the domestic client and principal designer agree in writing that the designer will perform them. If a domestic client makes no principal appointments, the designer and contractor in control of their phases take the respective roles. A business client retains its own client duties.
Arrange inspections and changes
Before starting notifiable building work, regulation 16 requires you to give the relevant authority “notice of intention to start work,” and work must not start until “at least two days have elapsed since the end of the day on which the notice was given.” This is the rule behind the practical figure GOV.UK gives applicants — that a Building Notice applicant “can start work 2 days after your notice has been submitted to your BCB” — and it governs the commencement of work on site, separately from whichever application route got building control involved in the first place.
Regulation 16 also lets the authority set inspection points specific to your job: having received your notice of intention to start work, it “may give the person carrying out the work a notice in writing which ... requires that person to notify the authority that a specified stage of the work ... has been reached.” Which stages get specified, and what notice each requires, is set out in that written notice for your project — it is not a fixed national list any guide can publish in advance. Ask your building control body for its written stage requirements as soon as you have a start date, and build those points into your programme rather than assuming a standard sequence applies.
That mechanism is what the ‘before covering work’ stage in the table above means in practice: alongside a specified stage, the authority can fix a period during which that work “must not be covered up.” The reason is straightforward — a foundation before backfill, or a structural connection before it’s boxed in, is only inspectable while exposed, and once the next trade covers it, checking compliance gets far harder or means opening the work up again later. Tell the relevant trades about the agreed hold points before they cover anything, and treat the inspection itself, not just “the work looks fine,” as what closes out that stage.
Keep a record of each inspection — what was checked, the outcome, and any action agreed — alongside the drawings and calculations you submitted. If an inspection raises a design question, that’s a matter for your designer to resolve with the building control body before the affected work proceeds; a formal building-control decision has its own procedure, and a RAMS review under CDM 2015 is not a way of disputing one. Where the design changes after the original submission, confirm with the building control body whether revised information or a further inspection is needed before building to the new detail.
Complete the records and handover
Completion runs on its own notice-and-certificate cycle. GOV.UK states “you’ll usually get a completion certificate within 8 weeks of completion of the building work, as long as it complies,” and that period is measured from when the authority receives the relevant completion notice rather than simply from the date the work finishes — so give whatever completion notice your building control body requires promptly, rather than assuming the clock starts by itself. The Regulations describe the certificate as “evidence (but not conclusive evidence)” that the relevant requirements have been met, not a document that overrides everything that came before it.
The authority issues the certificate once satisfied, “after taking all reasonable steps,” that the relevant requirements have been met — which means outstanding points from earlier inspections need to be closed out first, not carried forward and hoped past. Don’t commit a client to a fixed certificate date before your building control body has confirmed there’s nothing outstanding; the eight-week figure is what GOV.UK describes as the usual outcome once notice has been given and the work complies, not a turnaround fixed to the day work physically finishes.
Give the client the certificate, or the relevant completion documentation for whichever route you used, and keep an accessible copy alongside the rest of the project record — the submission, the drawings, the inspection notices and any written stage requirements. That documentation is evidence of the building-control history of the work; decisions a future buyer, lender or insurer makes about the property are theirs to make and sit outside the building-control process itself.
If work already went ahead without the required application or notice, regularisation is the retrospective route — available under regulation 18 only for work carried out on or after 11 November 1985, and, as GOV.UK states, “from a local authority BCB only”, not from a registered building control approver. It is an application for the local authority to assess the unauthorised work: regulation 18 lets the authority require you to take reasonable steps to show the work complies, which the regulation allows to include inspecting and testing it, before confirming whether further work is needed and, if satisfied, issuing a regularisation certificate. Submitting the application is not itself an approval, and it doesn’t make previously unauthorised work compliant on its own.
Planning the building-control evidence
Pros
- Full Plans gives a formal decision before you build — GOV.UK states 5 weeks, or 2 months with your consent.
- A Building Notice lets eligible smaller work start 2 days after the notice reaches the building control body.
- You can use the local authority via the Planning Portal or a registered building control approver.
- An agreed inspection plan tells the site team which work must stay visible until it is signed off.
- A shared record of drawings, changes and requests gives the client and designer a clear handover trail.
Cons
- A Building Notice gives no plans approval, so the technical risk sits with you at inspection.
- Plans approval does not remove the duty to make the actual work comply with building regulations.
- Charges are not set nationally — each authority publishes its own and approvers negotiate theirs.
- A generic inspection timetable may miss requirements specific to the project and application route.
- RAMS, an F10 or a software-generated pack cannot guarantee building-control acceptance.
| Stage | Prepare or confirm | Keep a record of |
|---|---|---|
| Before starting | Application route, design evidence and required notices | Submission, decisions, conditions and correspondence |
| Before covering work | Required inspection and relevant drawings or calculations | Visit outcome, outstanding questions and agreed actions |
| When the design changes | Designer input and building-control requirements for the change | Revised drawings, versions and agreed next steps |
| Completion | Outstanding actions, required certificates and declarations | The applicable completion documentation and client handover |
| Construction safety (separate) | CPP, risk assessment, safe methods and worker briefings | Current versions, reviews and site arrangements |
Frequently asked questions
Does an extension need building regulations approval?
Most domestic extensions need building regulations approval, and it is a separate process from planning permission — permitted development still has to meet the Building Regulations. The exemptions are narrow and conditional, not a floor-area rule of thumb. Schedule 2 of the Building Regulations 2010 exempts the addition at ground level of a conservatory, porch, covered yard or covered way, or a carport open on at least two sides, where that extension’s floor area does not exceed 30m² — and for conservatories and porches only where the glazing meets the Schedule 1 safety requirements. A detached single-storey building with no sleeping accommodation can be exempt up to 30m² where it stands at least a metre from the boundary or is built substantially of non-combustible material, and any detached building whose floor area does not exceed 15m², with no sleeping accommodation, is exempt. Schedule 2 exemption is not total: under regulation 9(3) the Part P electrical safety requirements still apply to a class 6 small detached building or a class 7 extension that receives its electricity from a source shared with or located inside a dwelling, and regulation 9(2) applies paragraphs G1 and G3(2) and (3) where the hot or cold water supply comes from a source shared with or inside any building that is not itself Schedule 2-exempt — so confirm the electrical and water arrangements with the building control body before treating the work as outside the Regulations. A standard single-storey rear extension, a loft conversion, a garage conversion or any two-storey extension is not exempt. This guide covers England: Wales has its own building regulations guidance, Scotland uses a building warrant, and Northern Ireland has separate building regulations.
What should I prepare before starting an extension?
Ask the building control body to confirm the appropriate application route and the evidence it needs for your design. This may include drawings, structural calculations, drainage details and information showing how relevant building regulations will be met. Confirm the applicable notices and inspection stages before programming the work. Prepare the separate construction-safety arrangements too. Under CDM 2015 in Great Britain every construction project needs a construction phase plan, whether or not it is notifiable: the principal contractor draws it up under regulation 12(1) where there is more than one contractor, and you draw it up under regulation 15(5) where you are the only contractor.
Does building control approve the contractor's RAMS?
Building control assesses compliance with building regulations; it is not a general RAMS approval service. A client or principal contractor may request and review RAMS for construction-safety coordination. A building control body may ask for information relevant to its own assessment, so clarify what is requested and why rather than ignoring it. A RAMS review, an F10 notification and building regulations approval are different processes.
How do Full Plans and a Building Notice differ?
A Full Plans application is assessed against the regulations before you build, and it is the route that gives you a formal decision to build to. GOV.UK states you can expect that decision within 5 weeks, or 2 months with your consent. A Building Notice suits eligible smaller work, gives no formal plans approval, and lets work start 2 days after the notice reaches your building control body — which leaves the technical risk with you at inspection, because an inspector can still require work to be opened up or removed. For work that is not higher risk you can apply to the local council through the Planning Portal, or to a registered building control approver, which submits an initial notice to the local authority on your behalf. Higher-risk building work goes to the Building Safety Regulator instead. Confirm eligibility and the required notices before assuming a submitted form lets you start.
How much will building control cost and how long will it take?
Charges are not set nationally, so get a current written quote: each local authority publishes its own charges, and registered building control approvers negotiate theirs. Ask what the quote covers, whether VAT applies, and how changes or extra visits are charged. Published decision periods apply to Full Plans applications, while charges vary by provider. On a Full Plans application GOV.UK states a decision within 5 weeks, or 2 months with your consent. For either local-authority route — Full Plans or Building Notice — a completion certificate should follow within eight weeks of the completion notice if the work complies. A private registered building control approver uses the final-certificate process; confirm the required evidence and outstanding actions with that approver. Book inspections with whatever notice period your building control body sets. There is no reliable universal saving or turnaround advantage for one provider type.
What if an inspection raises a problem or work has already started?
Ask for the outstanding issue and the evidence or remedial work required in writing. Involve the designer where a design change is needed, and agree any further inspection before covering the work. A formal building-control decision has its own procedure; it is not an appeal against a RAMS review. If required approval or notification was missed, contact the local authority promptly. Regularisation is the retrospective route, and it is available only from local authority building control and only for unauthorised work carried out on or after 11 November 1985. It is an application to have the work assessed, not an automatic approval, and it does not remove the need to make the work compliant — which can mean opening up finished work so it can be inspected.
Related guides
Asked for RAMS by Building Control?
Identify the requester and distinguish safety review from building-regulations decisions.
RAMS for a house extension
Plan task-level risks and safe methods for the actual site.
What is a construction phase plan?
Understand the project-wide safety arrangements that the CPP records.
Prepare the separate construction-safety paperwork
The Site Book helps you prepare RAMS and a CPP for your project. Review each draft against the work and the site arrangements. The documents support your planning; they do not provide building regulations approval.
Create your first free job packSources
- Building regulations approval — GOV.UK · Accessed 13 September 2026
- Building regulations approval: how to apply — GOV.UK · Accessed 13 September 2026
- Design and building work: meeting building requirements (England) — Building Safety Regulator · Accessed 13 September 2026
- Construction Phase Plan: guidance for small projects — HSE · Accessed 13 September 2026
- The Building Regulations 2010, Schedule 2 — exempt buildings and work — legislation.gov.uk · Accessed 13 September 2026
- The Building Regulations 2010, regulation 14A — determination of applications for building control approval with full plans — legislation.gov.uk · Accessed 15 September 2026
- The Building Regulations 2010, regulation 16 — notice of commencement and completion of certain stages of work — legislation.gov.uk · Accessed 15 September 2026
- The Building Regulations 2010, regulation 17 — completion certificates — legislation.gov.uk · Accessed 15 September 2026
- The Building Regulations 2010, regulation 18 — unauthorised building work (regularisation) — legislation.gov.uk · Accessed 15 September 2026
- The Construction (Design and Management) Regulations 2015, regulation 12 — construction phase plan (principal contractor duty) — legislation.gov.uk · Accessed 15 September 2026
- The Construction (Design and Management) Regulations 2015, regulation 15 — duties of contractors (sole contractor construction phase plan duty) — legislation.gov.uk · Accessed 15 September 2026
- The Building Regulations 2010, regulation 9 — exempt buildings and work — legislation.gov.uk · Accessed 14 September 2026